Disassembling a large crane for surface transport

April 07, 2022
RST large crane

Some of you may have become accustomed to seeing CC the Colossal Crane towering over the R Street NW construction site. Starting on or about Monday, April 11, 2022, we will say ‘goodbye’ to CC as the contractors will begin working after-hours to remove the large crane from the site. The crane will be disassembled during the day and transported at night between 11:00 p.m. and 5:00 a.m. to reduce traffic impacts. CC will be replaced with a smaller crane.  
   
Removing the crane will take approximately three nights to complete. The parts will be loaded and hauled on flatbed trucks to the Northeast Boundary Tunnel Project construction site, located just south of RFK Stadium. The trucks will be escorted by safety vehicles and flaggers to help navigate turns, if necessary. 

Important Traffic Information:    
•    The eastbound and westbound lanes of Rhode Island Avenue, NW will be closed between 6th and 7th Streets, NW during the hours between 11:00 p.m. and 5:00 a.m.  
•    Accommodation will be made for Fire/EMS, MPD vehicles, and Metro buses to pass through.    
•    All other vehicles will be detoured around the work zone.   
•    6th Street NW will remain open.

Motorists, pedestrians, and cyclists are urged to adhere to the posted detour signs and/or flaggers and to use caution when traveling around the work zone.   
There will be no other construction activities taking place during this time to ensure noise levels are within municipal limits, however, residents may notice transport activity past 11:00 p.m. between April 11 and April 13, 2022.   
 

Map of the detour route around the 100-block of Rhode Island Avenue NW

Project Details  
DC Water is constructing the Northeast Boundary Tunnel (NEBT) to connect with the existing sewer system, significantly mitigating sewer flooding while improving the water quality of the Anacostia River. The NEBT is the largest component of the Clean Rivers Project and starts just south of RFK Stadium and extends north to Rhode Island Avenue and west to R Street NW. To learn more about the NEBT project, please visit dcwater.com/nebp.    
Thank you for your continued support of the NEBT project. Should you have any questions and/or need more information, please contact us at the information below:

For more information, please contact  
Email: dccleanrivers@dcwater.com  
24/7 NEBT Hotline: (800) 988-6151  
Northeast Boundary Tunnel Project Website: dcwater.com/NEBP  
 

Latest News

Placeholder DC Water Image

Emergency repairs are progressing on a nine-foot sewer tunnel that has closed a section of 22nd St NW since early July. DC Water and its contractor have made significant repairs to reinforce the ...

Placeholder DC Water Image

Albemarle Street, NW: Roadway Closure and Detour Starts September 9th.

Placeholder DC Water Image

WASHINGTON, DC — DC Water’s Permit Operations has updated the process for requesting tap and meter sets. Customers and contractors are now required to submit tap and meter set requests together. In ...

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Latest Blog Post
One of DC Water's skimmer boats on the Anacostia River with the Frederick Douglass Bridge in the background.
The Power of Skimming: How DC Water Keeps Our Rivers Clear
Is anything more on-brand than a water utility having boats? We have several of them, performing an important public service and helping beautify our rivers.
Upcoming Meeting
Date
October 3, 2024
Time
Thursday, 1:30 PM

Upcoming Events

Oct 5
9:00 am - 3:00 pm
Oct 5
Oct 5
10:00 am - 2:00 pm