Potomac Interceptor Collapse
A section of the pipe opened to accommodate additional high-capacity pumps
  • Collapse of 72" diameter section of pipe caused overflow of more than 200 million gallons of wastewater into Potomac River.
  • Bypass system is now rerouting the wastewater around the collapse to limit overflows.
  • Work continues to clean out the pipe so crews can begin repairs.
  • DC Water is testing the river for E. Coli. The sampling results are posted below.
  • Drinking Water is not impacted.

An Open Letter from DC Water's CEO

On February 11, 2026, CEO and General Manager David L. Gadis addressed the Potomac Interceptor collapse in an open letter "to our neighbors, community partners, and everyone who cares deeply about the Potomac River and our shared commitment to the Potomac River." Please click the link below to read the letter.

An open letter from DC Water CEO David L. Gadis about the Potomac Interceptor

What Happened

On January 19, 2026, a section of the 54-mile Potomac Interceptor (PI) sewer line collapsed along Clara Barton Parkway, in Montgomery County, resulting in a significant overflow into the C & O Canal National Historical Park. The PI carries about 60 million gallons of wastewater daily from as far away as Dulles Airport to the Blue Plains Advanced Wastewater Treatment Plant in Southwest DC for treatment. 

DC Water crews and contractors began work immediately to construct a bypass to contain the overflow. The bypass was completed and activated on January 24, utilizing powerful pumps and the C&O Canal to reroute wastewater around the collapsed section of pipe and back into the sewer system. The focus now is on clearing debris from the damaged pipe so that crews can begin repairs. 

As work progresses at the site, we are working to develop cleanup and remediation plans, which remain in the early stages and will be focused on immediately impacted areas such as the canal, drainage channels and portions of the Potomac River. Cleanup measures will be determined in conjunction with federal, state, and local regulatory agencies.

DC Water is providing daily updates on the progress to clean out and repair the PI. You can see the latest information by clicking on the links on the right side of this page.

Bacteria Sampling

Utilizing a contracted environmental firm and certified laboratory, DC Water initiated daily sampling for E. Coli, an indicator bacterium, at six (6) locations beginning on Jan 29, 2026. To assess water quality conditions, sampling locations including the overflow area as well as upstream and downstream sites.  The locations are shown on the following map, and the results are provided in the table below.

Overall, results show mostly decreasing trends since the start of sampling.  Results at these sites, particularly the elevated concentrations observed at the overflow site in recent days, are expected as a result of limited overflow events that occurred. These are likely influenced by ice and snowmelt, which may increase system flows, contributing to overflow events during this emergency repair. Although the overflow is now mostly contained, E. coli levels are expected to continue fluctuating over time due to residual impacts from the incident and ongoing influences from weather conditions such as precipitation, snowmelt, temperature variability, and other natural sources of E. coli bacteria such as wildlife.

DC Water’s E. Coli Sampling Locations

Map shows 6 sampling locations

Water Quality in the Potomac River

DC Water is performing daily water quality sampling. It’s important to note that historically the E. coli levels in the Potomac and Anacostia rivers vary widely from day to day. Fluctuations in water quality are influenced by factors such as weather events, river flow, runoff, pollutants, and other sources discharging into waterways; and measurements taken much further downstream cannot be attributed solely to this incident.

For the Potomac River, historical water quality data shows E. coli levels may vary from a range as low as 10 MPN/100mL to as much as 5,000 MPN/100mL on a given day.

A more detailed explanation is posted on the District Department of Energy and Environment (DOEE) website at https://doee.dc.gov/release/potomac-interceptor-update-and-faqs

DC Water has added two new sampling locations to the daily sampling.  These locations add data points closer to the overflow site. The Minnie’s Island sample locations are approximately 0.54 miles from the overflow site compared to the Fletcher's location which is 5.2 miles from the overflow site. These sample locations provide a better understanding of the impact in the river near the collapse site and allow us to compare the main stem of the Potomac River (south side sample) to the inlet areas along the shoreline around Minnie’s Island (north side sample) where the water flows more slowly.

*Lab results are unavailable on weekends and will be provided the following Monday (excluding holidays). 

E. Coli (MPN/100 ml)      
Sample Date Old Anglers Inn
(upstream of collapse)
Near Drainage Channel @ Overflow (Swainson Island) Between Minnie's Island and north shore of Potomac River South Side of Minnie's Island Fletcher's Boathouse Georgetown @ Wisconsin Ave Anacostia @ S. Cap St National Harbor
1/29/2026 11 570,000 Not sampled Not sampled 14,300 18,600 2 <1
1/30/2026 4 60,000 Not sampled Not sampled 3,000 2,700 11 3
1/31/2026 3 30,000 Not sampled Not sampled 1,200 5,100 6 2
2/1/2026 27 80,000 Not sampled Not sampled 488 300 21 4
2/2/2026 6 242,000 Not sampled Not sampled 397 173 6 31
2/3/2026 4 460,000 Not sampled Not sampled 68 53 30 15
2/4/2026 5 210,000 Not sampled Not sampled 49 48 45 178
2/5/2026 1 77,000 Not sampled Not sampled 38 84 16 33
2/6/2026 22 242,000 Not sampled Not sampled 108 238 23 10
2/7/2026 15 86,600 Not sampled Not sampled 79 114 16 24
2/8/2026 15 130,000 Not sampled Not sampled 260 43 47 27
2/9/2026 16 730,000 Not sampled Not sampled 20 20 5 <1
2/10/2026 7 600,000 Not sampled Not sampled 17 20 2 2
2/11/2026 8 155,000 Not sampled Not sampled 3 19 <1 6
2/12/2026 5 105,000 Not sampled Not sampled 7 75 8 14
2/13/2026 7 155,000 Not sampled Not sampled 33 548 23 8
2/14/2026 3      141,000 Not sampled Not sampled <100 153 17 2
2/15/2026 2      199,000 Not sampled Not sampled 58 84 18 3
2/16/2026 76 173,000 Not sampled Not sampled 111 238 1550 138
2/17/2026 59 16,700 Not sampled Not sampled 3 387 23 88
2/18/2026 43 5,000 3,300 1,600 105 162 40 121
2/19/2026 49 15,200 17,800 14,800 387 435 128 62

Consistent with public health and U.S. Environmental Protection Agency standards, swimming is not recommended when E. coli levels exceed 410 MPN/100 mL.

Historical data indicate typical E. coli levels in the Potomac River can range from 10 to 5,000 MPN/100mL. Variability in E. coli results are common and are influenced by multiple factors, such as weather (rainfall/snow melt and associated runoff) and subwatershed activities and conditions, including aging sewer infrastructure and illicit discharges. 

Drinking Water is not Impacted

It’s important to note, DC Water's drinking water system is separate from the wastewater system, and we want to reassure the public the drinking water is safe, and water service is NOT affected by this incident. The overflow is downstream from the Washington Aqueduct’s (Aqueduct) intakes at Great Falls. In coordination with the Aqueduct, the intakes are also closed at Little Falls downstream. 

Avoid the Area

The public is reminded to avoid contact with untreated sewage as it may carry bacteria and viruses. Anyone who comes in contact with the wastewater overflow should:

Leave the area immediately.
Wash exposed skin thoroughly with soap and clean water.
Disinfect any affected areas or items.
Do not consume food or water that may have been exposed.
Seek medical attention if symptoms occur.
Report exposure to DC Water at (202) 612-3400.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Picture of new bike pedestrian path and traffic detour
New Path for Capital Crescent Trail Opens at Georgetown Waterfront Park

DC CLEAN RIVERS – POTOMAC RIVER TUNNEL PROJECT
If you bike, drive, or walk through Georgetown, we’ve got changes starting this week around the Potomac River Tunnel construction on Water Street NW. The Capital Crescent Trail has a new temporary detour through Georgetown Waterfront Park, open now for cyclists between 33rd and Potomac streets NW.

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting
Date
February 23, 2026
Monday, 9:30 AM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.