Emergency Water Outage
Feb 08, 2026 | 03:00 PM

Emergency Water Outage
Feb 08, 2026 | 02:00 PM

Emergency Water Outage
Feb 08, 2026 | 01:00 PM

DC Water awards $215M Pump Station contract to protect District waterways and the Chesapeake Bay

July 17, 2013

The DC Water Board of Directors recently approved one of the largest contracts in the Authority’s history, for the design and construction of facilities that will reduce nitrogen discharge to the Potomac River and Chesapeake Bay as well as bring relief from combined sewer overflows (CSOs) to the District’s waterways.

It is a design-build contract, a type growing in popularity for its ability to save time and money and create greater cooperation between contractor and owner. A Joint Venture of PC Construction and CDM Smith (PC/CDM Joint Venture) won the contract, estimated at nearly $215 million, based on a proposal that received the highest technical score and was the lowest cost.

When DC Water’s new permit limits for 2015 were first announced, DC Water analyzed possible solutions for lowering nitrogen to the required levels. The first proposal called for adding more nitrogen removal at Blue Plains and would have meant stacking treatment tanks on top of the existing ones. Instead, this innovative solution stores flow in the CSO tunnels so that even during peak flow (during wet weather) the flows can receive treatment. This design saved roughly $500 million.

The tunnel dewatering pump station is a complex pumping facility that will be built into the shaft that currently serves as an entrance to the tunneling process. It will be the equivalent of a 10-story building, built downwards underground, for the purpose of lifting the tons of combined sewage that will be conveyed in the tunnels after rainstorms up to surface level for treatment.

The contract also includes an enhanced clarification facility to treat up to 225 million gallons per day of excess flow during rainstorm events. The flow then can either be sent to secondary treatment or discharged to the Potomac.

DC Water Board of Directors Chairman Allen Y. Lew commented, “Right now there are several billion dollars in construction projects underway at the Blue Plains Advanced Wastewater Treatment Plant, and the most costly are federally mandated. These costs are borne mostly by our ratepayers; therefore, we continue to seek measures to lessen the rate increases. Supporting creative solutions and negotiating competitive contracts go a long way in achieving that mission.”

“We are pleased to work with PC/CDM Joint Venture on this important component of our wet weather plan,” said DC Water General Manager George S. Hawkins. “And we are proud of the innovative solutions we continue to put in place. The projects that make up the wet weather plan achieve both nitrogen reduction and CSO abatement to improve the health of our waterways. By combining separate goals into related projects, we will save hundreds of millions of dollars.”

"Our joint venture is excited to work with DC Water on this unique project in our nation’s capital," said Kevin McCarthy, president of PC Construction . “We look forward to being part of this massive project to protect the environment.”

For decades, DC Water has been a pacesetter in restoring the Potomac River and Chesapeake Bay by improving performance and treatment capabilities at the Blue Plains Advanced Wastewater Treatment Plant. Blue Plains has successfully achieved nitrogen removal since 1999 and was the first to achieve the Chesapeake Bay Agreement goal of 40 percent nitrogen reduction. The current projects further reduce nitrogen levels to the limits of technology.

For more information on CSO reduction, please view DC Water’s informational cartoon about the Clean Rivers Project, “A Drop’s Life." Additional information is available at http://www.dcwater.com/cleanrivers.

Latest News

Trench boxes at construction site for new pit accessing Potomac Interceptor Upstream

DC Water and its contractors continue to make progress constructing new access points to the Potomac Interceptor, one upstream of the damaged section, and an additional entry downstream to divert more wastewater flow from the pipe. These access points will allow crews to install a bulkhead, blocking flow in the pipe upstream of the collapsed area, keeping the site as dry as possible so crews can safely remove an extensive rock dam currently blocking the pipe.

Photo of giant rock and boulder removed

DC Water is releasing new findings regarding the environmental impacts following the January 19, collapse in a section of the Potomac Interceptor. Based on flow monitoring data collected before and after interim bypass pumping was activated, DC Water estimates approximately 243 million gallons of wastewater has overflowed from the collapse site.

Image of rock blockage taken by CCTV inside the Potomac Interceptor downstream of the collapse

Update on Extended Repairs, Safety Measures, and Water Quality Monitoring

Overnight CCTV inspection of the Potomac Interceptor revealed the blockage inside the collapsed sewer line is far more significant, showing a large rock dam stretching approximately 30 feet downstream of the original failure.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Picture of new bike pedestrian path and traffic detour
New Path for Capital Crescent Trail Opens at Georgetown Waterfront Park

DC CLEAN RIVERS – POTOMAC RIVER TUNNEL PROJECT
If you bike, drive, or walk through Georgetown, we’ve got changes starting this week around the Potomac River Tunnel construction on Water Street NW. The Capital Crescent Trail has a new temporary detour through Georgetown Waterfront Park, open now for cyclists between 33rd and Potomac streets NW.

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting
Date
February 19, 2026
Thursday, 9:30 AM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 40% of the last 3 payments made and in the new fiscal year 50% will be credited. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.