Piney Branch Tunnel

DC Water’s Piney Branch Tunnel


Piney Branch Tunnel

UPDATE: Piney Branch Parkway Reopens and Tunnel Work Proceeds

DC Water’s contractor has completed construction site preparation for the Piney Branch Tunnel project. On June 8, 2026, the relocated section of the Piney Branch Parkway was reopened between Arkansas Avenue NW and Beach Drive. With the Piney Branch Parkway relocated, the project can now proceed with shaft and tunnel work.

The above image shows the completed relocation of Piney Branch Parkway

Enhanced safety measures have also been put in place to protect drivers, cyclists and pedestrians. A new three-way stop has been added at Piney Branch Parkway and 17th Street. Rumble strips and jersey barriers with high-visibility reflective markings were installed as well to alert drivers of the new curve in the road.

The adjoining pedestrian and bike trail will be separated from the construction site by barriers and fencing. A raised crosswalk at the work zone entrance will also help pedestrians cross safely and there will be a defined path to guide cyclists through the area. Flaggers will also be on site when equipment or materials need to move across the road.

The trail along Piney Branch Parkway will be maintained for the duration of the project. Expect occasional short-duration closures. The roadway will be returned to the original alignment at the end of the project.

As part of the Clean Rivers Project, Piney Branch Tunnel will help keep combined stormwater and wastewater from being discharged into Piney Branch when the system exceeds capacity during heavy rains.  The tunnel, which begins at Park Road, will capture that overflow and send it DC Water’s Blue Plains Advanced Wastewater Treatment Plant. Once the tunnel is in service, it’s expected to cut overflow volume into Piney Branch by about 96% and the number of discharges from 25 times a year to only once, helping to protect public health and improve water quality in Piney Branch, Rock Creek, and the Potomac River.

Piney Branch Tunnel Project

DC Water’s Clean Rivers Project is constructing the Piney Branch Tunnel Project within Rock Creek Park in northwest Washington, DC.  The tunnel will capture and store a minimum of 4.2-million gallons of sewage combined with stormwater, known as combined sewer overflow (CSO), that will otherwise overflow into Piney Branch when the capacity of the existing combined sewer system is exceeded during storms. The United States Environmental Protection Agency (USEPA) currently lists Piney Branch as an impaired waterbody under the Clean Water Act.

The Piney Branch Tunnel Project will comply with the 2005 Federal Consent Decree entered into by DC Water, the District, the USEPA, and the US Department of Justice, as amended January 2016, and modified December 2020. The project is designed to improve water quality in Piney Branch, Rock Creek, and ultimately the Potomac River and Chesapeake Bay by reducing untreated discharges to the sewer system and increasing sewer overflow storage and conveyance capacity.

Currently, an estimated 40 million gallons of untreated combined sewer discharge overflows into Piney Branch in a year of average rainfall during heavy storm events. This harms local waterways and wildlife. Once completed, the Piney Branch Tunnel will capture and store most of this overflow during storms, reducing these overflows by 96% and limit the frequency of overflow events from 25 to one in a year of average rainfall.

The project includes construction of a diversion structure at the Piney Branch outfall, known as CSO 049, to redirect sewer flows to the storage tunnel. A structure will also be constructed adjacent to Park Road NW to discharge the combined sewage from the tunnel back into the existing sewer system to DC Water’s Blue Plains Advanced Wastewater Treatment Plant for treatment when the system can handle the volume. 


Schedule

Procurement 2024-2025
Construction 2025-2029

Environmental Assessment (EA) and Finding of No Significant Impact (FONSI)

DC Water and the National Park Service (NPS) prepared an Environmental Assessment (EA) to comply with the National Environmental Policy Act (NEPA). The EA analyzed and evaluated potential environmental impacts associated with the project. NPS also elicited public comments on the EA. NPS considered two alternatives in the EA, a no-action alternative and a proposed action alternative, the construction of the Piney Branch Tunnel.

Following extensive review, the National Park Service (NPS) approved DC Water’s proposal to construct the Piney Branch Tunnel on NPS land in Rock Creek Park. A Finding of No Significant Impact (FONSI) was signed on March 5, 2025, selecting the construction of the Piney Branch Tunnel. The FONSI describes the rationale for the decision and outlines measures that will be taken to avoid, minimize and mitigate any impacts. The Environmental Assessment and Finding of No Significant Impact can be viewed at https://parkplanning.nps.gov/dcPineyBranch.

Just The Facts
4.2
Million-gallon storage Tunnel

Stay connected with us through these convenient options:

Project Number 202-787-4400
Project Email dcpineybranch@dcwater.com
Call DC Water Emergency Services for urgent water or sewer issues or to report a dry weather overflow at any time, 202-612-3400.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Photo of temporarily relocated section of Piney Branch Parkway
Piney Branch Parkway Section to Reopen Monday, Restoring a Key Route for DC Commuters

Following a 27-day closure, DC Water will reopen a section of Piney Branch Parkway between Arkansas Avenue and Beach Drive NW early Monday morning, restoring an important cross-town connection for thousands of District commuters. During the closure, a section of the road was temporarily relocated for construction of DC Water’s Piney Branch Tunnel Project.

Latest Blog Post
DC Water General Manager and CEO David Gadis recognizes Lily MacDonald during the May Board of Directors meeting.
From Classroom to Community: A Student Spotlight on DC Water's SPLASH Program
A speechwriting assignment became a call to action for water access and affordability through DC Water's SPLASH program.
Upcoming Meeting
Date
July 2, 2026
Thursday, 9:30 AM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.