EMERGENCY WATER OUTAGE
Feb 08, 2026 | 01:00 AM

EMERGENCY WATER OUTAGE
Feb 07, 2026 | 11:00 PM

Emergency Water Outage
Feb 07, 2026 | 04:00 PM

DC Water’s tunnel boring machine Lucy makes it home for the holidays

December 22, 2015

If you thought holiday traffic was bad, consider this—it took DC Water’s tunnel boring machine named Lucy five months to travel 2,700 feet. Granted, she did it about 100 feet below ground and had to cut her way through 500 million pounds of sand, silt and clay. Lucy mined under First Street, NW, from Channing Street to Rhode Island Avenue, to create the First Street Tunnel. This tunnel segment will ultimately connect to the five-mile-long Northeast Boundary Tunnel in 2022.

“We are pleased to reach this important milestone in the project and are grateful for the continued patience of the impacted community,” said DC Water CEO and General Manager George Hawkins. “We will continue to work with the neighborhood to complete this essential project as soon as possible to provide flood relief for residents.”

From 2016 to 2022 the First Street Tunnel will store and then pump combined sewage up into the existing sewer system during and after rainstorms to keep it off of streets and out of basements. The First Street Tunnel is designed to mitigate flooding from undersized sewers in the Bloomingdale and LeDroit Park neighborhoods. It is part of the DC Clean Rivers Project aimed at significantly reducing combined sewer overflows to District waterways.

DC Water selected Skanska/Jay Dee Joint Venture for the project in 2013. Lucy was christened in a ceremony in April of this year and began her dig this summer. Scott Hoffman, Skanska/Jay Dee Project Manager for the First Street Tunnel said the joint venture team was committed to this project and the challenge of conducting heavy civil work in a densely populated urban area. “We’re proud of the end result, and the positive impact it will have on the community,” Hoffman said. “It’s a great accomplishment to have Lucy finish the tunneling portion of the work just in time for her to go home for the holidays.”

Lucy was named honoring Lucy Diggs Slowe (1895-1937), a District of Columbia local and the First Dean of Women at Howard University in 1922. There, she established a women’s campus and influenced the appointment of women’s deans throughout the country. Prior to that, Ms. Diggs Slowe founded – and served as principal for—Shaw Junior High School in 1919, the first junior high in the District of Columbia school system. She was a founding member of Alpha Kappa Alpha Sorority, Inc. and was inducted into the 26th annual Maryland Women’s Hall of Fame. In addition, she was a decorated athlete, winning the American Tennis Association’s first tournament in 1919, making her the first African-American woman to win a major sports title.

This is the second DC Water tunnel boring machine to complete her mission this year. In July, Lady Bird completed a two-year, 4.5 mile trek to dig the Blue Plains tunnel segment.

Now Lucy will be dismantled and 99 percent of her parts will be recycled, while the tunnel she dug is prepared for use. Work also continues to connect the existing sewers along First Street, NW to the new tunnel. For more information on the project, please visit: dcwater.com/firststreettunnel.

Latest News

Trench boxes at construction site for new pit accessing Potomac Interceptor Upstream

DC Water and its contractors continue to make progress constructing new access points to the Potomac Interceptor, one upstream of the damaged section, and an additional entry downstream to divert more wastewater flow from the pipe. These access points will allow crews to install a bulkhead, blocking flow in the pipe upstream of the collapsed area, keeping the site as dry as possible so crews can safely remove an extensive rock dam currently blocking the pipe.

Photo of giant rock and boulder removed

DC Water is releasing new findings regarding the environmental impacts following the January 19, collapse in a section of the Potomac Interceptor. Based on flow monitoring data collected before and after interim bypass pumping was activated, DC Water estimates approximately 243 million gallons of wastewater has overflowed from the collapse site.

Image of rock blockage taken by CCTV inside the Potomac Interceptor downstream of the collapse

Update on Extended Repairs, Safety Measures, and Water Quality Monitoring

Overnight CCTV inspection of the Potomac Interceptor revealed the blockage inside the collapsed sewer line is far more significant, showing a large rock dam stretching approximately 30 feet downstream of the original failure.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Picture of new bike pedestrian path and traffic detour
New Path for Capital Crescent Trail Opens at Georgetown Waterfront Park

DC CLEAN RIVERS – POTOMAC RIVER TUNNEL PROJECT
If you bike, drive, or walk through Georgetown, we’ve got changes starting this week around the Potomac River Tunnel construction on Water Street NW. The Capital Crescent Trail has a new temporary detour through Georgetown Waterfront Park, open now for cyclists between 33rd and Potomac streets NW.

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting
Date
February 19, 2026
Thursday, 9:30 AM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 40% of the last 3 payments made and in the new fiscal year 50% will be credited. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.