Emergency Water Outage
Dec 31, 2025 | 05:24 PM

EMERGENCY WATER OUTAGE
Dec 31, 2025 | 04:00 PM

INSPECTOR GENERAL(IG)ISSUES FINAL REPORT

June 04, 2004

The District of Columbia’s Inspector General (IG) issued its final report on the Audit of Residential Customer Billing for Water Usage and the Customer Complaint Process, and concluded that the District of Columbia Water and Sewer Authority’s (WASA) bills are accurate and its meters accurately measure consumption.

As a result of some customers’ complaints and hearings held before Councilmember Carol Schwartz’s Public Works and the Environment Committee last year, Jerry N. Johnson, WASA General Manager, requested the Inspector General to conduct an investigation to test the accuracy of meter technology, to validate the accurate transmission of customer bills, and WASA’s customer responsiveness.

The IG conducted its first audit report to address issues related to WASA’s residential water meters and the accuracy of the new residential water meters. The results of the audit were issued on December 23, 2003 and concluded the District’s residential water meter readings are accurately recording water flow and accurately transmitting water meter readings to WASA’s receiving units.

The second issue the IG investigated related to the accuracy of the customer billing system for the new automated meter reading (AMR) and the efficiency and effectiveness of the customer complaint process. The results showed that WASA accurately processed residential customer billings that reflected the water usage reported electronically from the water meters. The IG concluded that WASA could improve the process for responding to customer complaints, and did cite seven separate minor examples where WASA customer responsiveness could be increased. In all cases the issues cited were addressed prior to the conclusion of the IG’s review.

“This completes the review of our AMR project, and we are pleased with the findings of the Inspector General,” stated Jerry N. Johnson, WASA General Manager. “The IG found that our new meters accurately measure water usage and that the automated meter reading (AMR) technology accurately transmits these readings to our customer billing system. We have taken the corrective action to address all the issues cited in the audit report to improve our customer service efforts.”

WASA has installed a total of 111,668 new meters (90% of its customers) in the District of Columbia. The meter exchange is to be completed at the end of 2004.

Latest News

Photo of a worker on the slope an the slope with hydroseeding completed

Major Milestone Paves Way for Potomac River Tunnel Construction at the Site

DC Water has completed its slope stabilization project along Canal Road, a critical step in order to move forward with construction for the Potomac River Tunnel Project. Originally scheduled to end in February, the project finished about two months ahead of schedule, minimizing additional impacts to commuters and residents.

Picture of frozen water pipes with icicles hanging off of them

With December getting off to a near-record cold start now is the time to act. Winter weather can bring risks like frozen pipes, water main breaks, and other emergencies that can disrupt your water service. Don’t wait for something to happen. DC Water encourages customers to prepare now and know what to do if the unexpected happens.

Worker on side of steep slope

TRAFFIC ADVISORY - CLEAN RIVERS - POTOMAC RIVER TUNNEL PROJECT

DC Water is in the final stretch of its slope stabilization project along Canal Road NW, a critical project that will pave the way for Potomac River Tunnel construction at this site. Beginning, the week of December 15, 2025, one westbound lane of Canal Road will be closed during daytime, off-peak hours on weekdays and Saturdays to hydroseed the slope.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Photo of a worker on the slope an the slope with hydroseeding completed
DC Water Announces Early Completion of Canal Road Slope Stabilization Project

Major Milestone Paves Way for Potomac River Tunnel Construction at the Site

DC Water has completed its slope stabilization project along Canal Road, a critical step in order to move forward with construction for the Potomac River Tunnel Project. Originally scheduled to end in February, the project finished about two months ahead of schedule, minimizing additional impacts to commuters and residents.

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 40% of the last 3 payments made and in the new fiscal year 50% will be credited. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.