EMERGENCY WATER MAIN REPAIR
Feb 08, 2026 | 05:30 AM

EMERGENCY WATER MAIN REPAIR
Feb 08, 2026 | 04:30 AM

EMERGENCY WATER MAIN REPAIR
Feb 08, 2026 | 04:00 AM

TRAFFIC ADVISORY: Northbound Lane on 22nd St NW Reopens, Emergency Sewer Repairs Ongoing

February 03, 2025
Photo of construction area at 22nd and Q streets NW with one northbound lane open

Remaining lane closures to continue 22nd St NW from Massachusetts Ave to P St and Florida Ave NW

Repairs are progressing on a nine-foot sewer tunnel that has closed a section of 22nd St NW since early July, allowing DC Water and its contractor to reopen one northbound lane of this key corridor to vehicular traffic. Emergency repairs are expected to continue for another six months pending weather or unforeseen issues that affect the schedule. During this time, the remaining lanes will be closed, however, portions of the road may reopen as work progresses.

Since July, DC Water and its contractor have made significant repairs to reinforce the tunnel which had significant structural issues and was in danger of collapse. The 140-year-old cobblestone pipeline had longitudinal cracks, missing cobblestones and bricks, root penetration, and a large void in the soil around the tunnel compromising the road above. 

DC Water is working closely with the District Department of Transportation to minimize the disruption in the area while additional repairs are made. As construction continues, the southbound lane on 22nd St NW will remain closed with one northbound lane open to thru traffic between P St NW and Massachusetts Ave NW. Additional changes to the traffic pattern and lane closures may be necessary as work moves to other areas of the pipeline and tunnel.

DC Water DC Water operates approximately 2,000 miles of combined, separate, and stormwater sewers. Original parts of the system date back more than 200 years and the Authority is making significant investments to update and modernize our stormwater and sewer infrastructure as part of the 10-year, $7.7 billion Capital Improvement Plan.

The repairs are designed to address defects subsequently found upstream and downstream of the main void that initiated emergency work in July 2024. With the initial phase of the emergency repairs complete, work has begun on a second phase to address urgent repairs due to cracks upstream and downstream as well as additional voids in the soil surrounding the pipes.

Crews may work night and day, 24 feet below ground inside the sewer tunnel, with construction taking place seven days a week. Over 115,000 linear feet of rebar (including 11,400 rebar anchors) will be installed and the tunnel sprayed with 675 tons of shotcrete, a high-pressure concrete material, to reinforce and support the pipe.

Motorists and cyclists are advised to follow detour signage. 

The repairs to DC Water’s aging infrastructure will ensure the system is sustainable, equitable, reliable, resilient and supports health, safety, and well-being. We appreciate your patience while we get this important work done.

Traffic and Cyclist Detour:

  • Motorists and cyclists are directed to follow detour signage (see map below):
    • Northbound from Florida Ave NW turn east on Massachusetts Ave NW to us Dupont Circle to P St NW or Connecticut Ave NW.
    • From P St NW, use one lane Northbound on 22nd St NW to Florida Ave or turn east Massachusetts Ave NW to Dupont Circle.
    • Partial lane closure at the intersection of Florida Ave NW and R St NW, turn east on R St NW to Connecticut Ave NW then to Dupont Circle, to access westbound Massachusetts Ave NW and P westbound P St NW.
  • Southbound 22nd St NW Q St NW and P St NW will remain closed for the duration of the repairs.

Anticipated Schedule:

  • February 2025 – July 2025 repairs to mitigate defects found in the pipeline, including longitudinal cracks, missing cobblestones, root penetration, and missing bricks.
  • February 2025 – Northbound lane opens to through traffic.
  • July 2025 – anticipated completion of repairs, road reopens (subject to weather or other unforeseen delays)

Work includes shoring, LIDAR scanning, soil stabilization, structural upgrades, excavation, backfill and reconstruction of the roadway. 

Map of detours around southbound lane closure at Q & 22nd streets Northwest
*Map updated 03/11/25

People who live or work near the affected locations will notice additional construction equipment and personnel as well as noise associated with construction activities.

For any questions or concerns, please contact our DC Water 24-hour Emergency Command Center at 202-612-3400.

Latest News

Trench boxes at construction site for new pit accessing Potomac Interceptor Upstream

DC Water and its contractors continue to make progress constructing new access points to the Potomac Interceptor, one upstream of the damaged section, and an additional entry downstream to divert more wastewater flow from the pipe. These access points will allow crews to install a bulkhead, blocking flow in the pipe upstream of the collapsed area, keeping the site as dry as possible so crews can safely remove an extensive rock dam currently blocking the pipe.

Photo of giant rock and boulder removed

DC Water is releasing new findings regarding the environmental impacts following the January 19, collapse in a section of the Potomac Interceptor. Based on flow monitoring data collected before and after interim bypass pumping was activated, DC Water estimates approximately 243 million gallons of wastewater has overflowed from the collapse site.

Image of rock blockage taken by CCTV inside the Potomac Interceptor downstream of the collapse

Update on Extended Repairs, Safety Measures, and Water Quality Monitoring

Overnight CCTV inspection of the Potomac Interceptor revealed the blockage inside the collapsed sewer line is far more significant, showing a large rock dam stretching approximately 30 feet downstream of the original failure.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Picture of new bike pedestrian path and traffic detour
New Path for Capital Crescent Trail Opens at Georgetown Waterfront Park

DC CLEAN RIVERS – POTOMAC RIVER TUNNEL PROJECT
If you bike, drive, or walk through Georgetown, we’ve got changes starting this week around the Potomac River Tunnel construction on Water Street NW. The Capital Crescent Trail has a new temporary detour through Georgetown Waterfront Park, open now for cyclists between 33rd and Potomac streets NW.

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting
Date
February 19, 2026
Thursday, 9:30 AM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 40% of the last 3 payments made and in the new fiscal year 50% will be credited. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.