TRAFFIC ADVISORY: Northbound Lane on 22nd St NW Reopens, Emergency Sewer Repairs Ongoing

February 03, 2025
Photo of construction area at 22nd and Q streets NW with one northbound lane open

Remaining lane closures to continue 22nd St NW from Massachusetts Ave to P St and Florida Ave NW

Repairs are progressing on a nine-foot sewer tunnel that has closed a section of 22nd St NW since early July, allowing DC Water and its contractor to reopen one northbound lane of this key corridor to vehicular traffic. Emergency repairs are expected to continue for another six months pending weather or unforeseen issues that affect the schedule. During this time, the remaining lanes will be closed, however, portions of the road may reopen as work progresses.

Since July, DC Water and its contractor have made significant repairs to reinforce the tunnel which had significant structural issues and was in danger of collapse. The 140-year-old cobblestone pipeline had longitudinal cracks, missing cobblestones and bricks, root penetration, and a large void in the soil around the tunnel compromising the road above. 

DC Water is working closely with the District Department of Transportation to minimize the disruption in the area while additional repairs are made. As construction continues, the southbound lane on 22nd St NW will remain closed with one northbound lane open to thru traffic between P St NW and Massachusetts Ave NW. Additional changes to the traffic pattern and lane closures may be necessary as work moves to other areas of the pipeline and tunnel.

DC Water DC Water operates approximately 2,000 miles of combined, separate, and stormwater sewers. Original parts of the system date back more than 200 years and the Authority is making significant investments to update and modernize our stormwater and sewer infrastructure as part of the 10-year, $7.7 billion Capital Improvement Plan.

The repairs are designed to address defects subsequently found upstream and downstream of the main void that initiated emergency work in July 2024. With the initial phase of the emergency repairs complete, work has begun on a second phase to address urgent repairs due to cracks upstream and downstream as well as additional voids in the soil surrounding the pipes.

Crews may work night and day, 24 feet below ground inside the sewer tunnel, with construction taking place seven days a week. Over 115,000 linear feet of rebar (including 11,400 rebar anchors) will be installed and the tunnel sprayed with 675 tons of shotcrete, a high-pressure concrete material, to reinforce and support the pipe.

Motorists and cyclists are advised to follow detour signage. 

The repairs to DC Water’s aging infrastructure will ensure the system is sustainable, equitable, reliable, resilient and supports health, safety, and well-being. We appreciate your patience while we get this important work done.

Traffic and Cyclist Detour:

  • Motorists and cyclists are directed to follow detour signage (see map below):
    • Northbound from Florida Ave NW turn east on Massachusetts Ave NW to us Dupont Circle to P St NW or Connecticut Ave NW.
    • From P St NW, use one lane Northbound on 22nd St NW to Florida Ave or turn east Massachusetts Ave NW to Dupont Circle.
    • Partial lane closure at the intersection of Florida Ave NW and R St NW, turn east on R St NW to Connecticut Ave NW then to Dupont Circle, to access westbound Massachusetts Ave NW and P westbound P St NW.
  • Southbound 22nd St NW Q St NW and P St NW will remain closed for the duration of the repairs.

Anticipated Schedule:

  • February 2025 – July 2025 repairs to mitigate defects found in the pipeline, including longitudinal cracks, missing cobblestones, root penetration, and missing bricks.
  • February 2025 – Northbound lane opens to through traffic.
  • July 2025 – anticipated completion of repairs, road reopens (subject to weather or other unforeseen delays)

Work includes shoring, LIDAR scanning, soil stabilization, structural upgrades, excavation, backfill and reconstruction of the roadway. 

Map of detours around southbound lane closure at Q & 22nd streets Northwest
*Map updated 03/11/25

People who live or work near the affected locations will notice additional construction equipment and personnel as well as noise associated with construction activities.

For any questions or concerns, please contact our DC Water 24-hour Emergency Command Center at 202-612-3400.

Latest News

Workers putting down rye and matting for soil stabilization
  • More than one month after the last overflow into the Potomac River, DC Water is preparing to return flow in the coming days to the Potomac Interceptor and meet the mid-March target to complete the ...
Tree and debris removal for environmental rehabilitation

Work is nearly complete on the downstream section of the Potomac Interceptor to reinforce the pipeline with geopolymer. The concrete-like material will strengthen and restore the structural integrity of the pipe. Completion of the geopolymer lining downstream is one of the final steps to restore flow to the interceptor and finish the emergency repair.

This comes one month since the last overflow reached the Potomac River.

geopolymer downstream

As emergency repairs continue, today marks 27 days, nearly one month, with no overflow reaching the Potomac River.

Crews are making significant progress to reinforce the downstream section of pipe from the collapse site and completed 240 linear feet of geopolymer overnight. Crews are working to apply another layer of geopolymer today. The material is similar in strength to concrete and when applied restores the structural integrity of the pipe.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Picture of new bike pedestrian path and traffic detour
New Path for Capital Crescent Trail Opens at Georgetown Waterfront Park

DC CLEAN RIVERS – POTOMAC RIVER TUNNEL PROJECT
If you bike, drive, or walk through Georgetown, we’ve got changes starting this week around the Potomac River Tunnel construction on Water Street NW. The Capital Crescent Trail has a new temporary detour through Georgetown Waterfront Park, open now for cyclists between 33rd and Potomac streets NW.

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting
Date
March 11, 2026
Wednesday, 9:30 AM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.