WASA AND DC FIRE DEPARTMENT REACH AGREEMENT ON ACTUAL NUMBER OF OUT-OF-SERVICE HYDRANTS

November 16, 2007

The District of Columbia Water and Sewer Authority (WASA) and DC Fire and Emergency Medical Services (FEMS) have reconciled the actual number of out-of-service fire hydrants to conclude the 2007 hydrant assessment program.

Fire officials produced a list of 235 out-of-service fire hydrants at an October 31, 2007 City Council hearing. On that day, WASA’s computerized asset management system, which is updated daily, listed only 62 out-of-service hydrants – less than one percent of the 9,095 public hydrants in the District that are maintained by WASA.

Both agencies worked collaboratively during the past two weeks to reconcile the differences between their respective lists. After a thorough review of collected data, site visits and field testing, WASA and FEMS agreed on a total of 29 out-of-service public hydrants from the October 31 lists.

A number of factors contributed to the reporting discrepancies between the two agencies. The FEMS list contained hydrants that are privately owned, hydrants that had been abandoned, and some that had been returned to service. For example, WASA maintains a public hydrant inventory and reports weekly on the operational status of public hydrants. However, WASA does not maintain the inventory of private hydrants in the District since the repair and maintenance of these hydrants is the owner’s responsibility. In addition, some public hydrants that were relocated and replaced due to capital construction work or accessibility issues were reported by FEMS as missing during the hydrant assessment program and were included on their list as out-of-service.

Private hydrants and abandoned hydrants accounted for 154 reporting differences between the two lists. The remaining differences were mostly related to reporting issues between the two agencies that have since been corrected during the reconciliation process.

As of November 16, 2007, there are 56 public out-of-service hydrants. This number includes those recently taken out of service by WASA as a result of its flushing program, customer-reported problems and other capital construction work. This out-of-service number can change daily, based on field conditions and completed hydrant work. WASA and FEMS are holding monthly operational meetings to improve communications and prepare for the 2008 hydrant inspection and assessment program.

Latest News

Photo of workers doing environmental rehab in west section of Area 1

With 32 days of no overflows reaching the Potomac River, DC Water and its contractor continue to make progress on the Environmental Rehabilitation of the areas impacted by the failure in the Potomac Interceptor. Meanwhile work is nearing completion in the coming days on the emergency repair and is expected to meet the mid-March target.

photo of worker going into downstream cleaning pit
  • Work is progressing to meet the mid-March target to return the flow to the Potomac Interceptor, as we reach 31 days with no overflows reaching the Potomac River.
  • The geopolymer applied to the upstream ...
Workers putting down rye and matting for soil stabilization
  • More than one month after the last overflow into the Potomac River, DC Water is preparing to return flow in the coming days to the Potomac Interceptor and meet the mid-March target to complete the ...

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Picture of new bike pedestrian path and traffic detour
New Path for Capital Crescent Trail Opens at Georgetown Waterfront Park

DC CLEAN RIVERS – POTOMAC RIVER TUNNEL PROJECT
If you bike, drive, or walk through Georgetown, we’ve got changes starting this week around the Potomac River Tunnel construction on Water Street NW. The Capital Crescent Trail has a new temporary detour through Georgetown Waterfront Park, open now for cyclists between 33rd and Potomac streets NW.

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting
Date
March 19, 2026
Thursday, 9:30 AM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.