WASA Board Intensifies Efforts to Protect Potomac River and Chesapeake Bay

April 05, 2007

The District of Columbia Water and Sewer Authority (WASA) Board of Directors has given the green light to two projects at the Blue Plains Advanced Wastewater Treatment Plant that will have a significant impact on WASA’s ongoing program to reduce nitrogen levels discharged from the sewage treatment plant into the Potomac River, a tributary of the Chesapeake Bay. Nitrogen is a key pollutant that causes the depletion of oxygen that fish and other aquatic life need to thrive.

The board’s action today approves a $101 million construction contract to replace, rehabilitate and upgrade facilities at Blue Plains to continue the 40 percent reduction levels that WASA has voluntarily achieved. The board also authorized the general manager to submit a plan, estimated to cost more than $800 million, to further reduce nitrogen levels to meet the new limit set by the U.S. Environmental Protection Agency (EPA) in its modification of the Blue Plains operating permit. The new permit limit requires a reduction of total nitrogen (TN) from the plant from 8.5 million pounds per year to 4.7 million pounds per year. The cost will be shared between the District rate payers and the Authority’s suburban wastewater treatment customers in Maryland and Virginia.

“After months of discussions by the board, meetings with stakeholders and other regional interests, and negotiations with EPA, the board has embraced a conceptual plan that is very aggressive and very expensive,“ General Manager Jerry N. Johnson said.

The Blue Plains wastewater plant, the largest single point source discharger to the Chesapeake Bay, treats an average 370 millions of gallons per day and has been a leader in voluntarily reducing nutrient (nitrogen and phosphorus) discharge. WASA has reduced nitrogen levels by 75 percent since 1987, far exceeding goals established by the Chesapeake Bay Agreement in 1987 and 2000. Since 2000, WASA has met its voluntary goal of 7.5 million pounds of TN per year and, for the past two years, through research and related improved operations, has averaged less that 5.5 million pounds per year.

“In terms of the effort and money spent on protecting and cleaning up the Potomac and Anacostia rivers and the Chesapeake Bay estuary, we are true environmental stewards, making a significant investment in resolving longstanding problems,” Johnson said.

Johnson further referenced the 2005 Chesapeake Bay Commission Report which documents that less than 26 percent of the Bay’s nitrogen is due to discharges from municipal wastewater treatment plants. “It is clear that reduction in other sources of nitrogen -- agriculture, animal waste, fertilizers, and the atmosphere –has to be addressed if the Bay restoration program is to succeed. It can’t all be done on the backs of the municipalities,” he said.

WASA will submit its proposed reduction strategy to EPA Region III by April 16, 2007. WASA will also submit the plan to the environmental organizations that commented on the draft permit. The implementation schedule for the proposed plan will be established through continuing discussions with EPA.

Latest News

Map: Temporary southbound lane closure on Rock Creek and Potomac Parkway NW.

Starting on or about Aug. 7, 2026, weather permitting, drivers can expect a temporary lane closure southbound on Rock Creek and Potomac Parkway NW near the intersection of Virginia Avenue NW and F ...

Photo of inside Potomac Interceptor at Dulles showing newly lined tunnel

First of four emergency repairs on Potomac Interceptor finished

DC Water has finished the first of four emergency repair projects on the Potomac Interceptor sewer line. Crews completed work today to strengthen a 600-foot section of pipe at Dulles International Airport.

Picture of repaired segment before the geopolymer work and after the work is done

Crews also reach a major milestone near Dulles International Airport as the next phase of repairs begins this week

DC Water has completed the first major step in emergency repairs to a 175-foot section of the Potomac Interceptor near Pennyfield Lock in Potomac, Maryland. Crews added a new, stronger lining inside the pipe after inspections found serious wear and damage. The work is part of ongoing repairs to 1,700 linear feet of pipe near Pennyfield Lock. Work began on Friday to apply geopolymer, a concrete-like material, inside the pipe. With the new lining complete, crews are preparing for the next phase of work for the remainder of the pipe segment.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Latest Blog Post
Plastic bottles, cups and other floating debris on the surface of the Anacostia River before the Anacostia River Tunnel began operating.
Cleaner Waterways Start With Everyday Choices
Protecting our waterways starts with everyday actions and continues through critical infrastructure designed to keep pollution out of our rivers.
Upcoming Meeting

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.