Following review and consideration of public input during a 30-day public comment period, EPA approves the IUP and PPL of drinking water projects that are eligible to receive federal funding under Section 1452 of the Safe Drinking Water Act.
EPA announced the availability of the IUP and PPL for public comment on April 23, 2021 via our website. EPA also sent an email to each of the Advisory Neighborhood Commissions as well as the DC Mayor’s office, Congresswoman Norton’s office, the DC Council, and relevant city agencies.
The funding for the proposed projects identified in the IUP and PPL will be awarded as grants to assist the District of Columbia in updating and improving drinking water infrastructure. The PPL presents the long-term strategy, while the IUP is focused on how funds will be expended in the immediate future during FYs 2021 and 2022. Projects were rated on their contribution to public health, compliance with regulatory standards, and maintaining drinking water reliability, safety, and environmental protection.
The universe of projects identified in the approved IUP that may be submitted for federal grant funding is shown in the following table.
Project Pool that may be submitted for grants during FY 2021 & FY 2022 (in priority ranking order) |
||
Project | Fiscal Year | Grant Funding |
---|---|---|
Anacostia Elevated Tank #1 Upgrades | FY 2021 | $3,148,000 |
66-inch/72-inch PCCP N Street (Water Mains Rehab Phase I) | FY 2021 | $4,212,000 |
Small Diameter Water Main Rehab 14C | FY 2021 | $12,544,864 |
Constitution Ave NE w C9 | FY 2021 | $1,048,000 |
Small Diameter Water Main Rehab 15A | FY 2022 | $10,380,000 |
Small Diameter Water Main Rehab 15B | FY 2022 | $11,172,000 |
Small Diameter Water Main Rehab 15D | FY 2022 | $13,960,000 |
Small Diameter Water Main Rehab 12C | FY 2021 | $9,276,000 |
Small Diameter Water Main Rehab 16A | FY 2022 | $11,924,000 |
Small Diameter Water Main Rehab 16B | FY 2022 | $11,600,000 |
Small Diameter Water Main Rehab 16C | FY 2022 | $12,400,000 |
Small Diameter Water Main Rehab 18A | FY 2022 | $9,600,000 |
Bryant Street PS – Spill Header Flow Control | FY 2022 | $6,200,609 |