SMALL DIAMETER WATER MAIN REPLACEMENT PROJECT BRIGHTWOOD NEIGHBORHOOD – ADVISORY NEIGHBORHOOD COMMISSION 4B

150050_8-Inch Valve and piping at Edgewood-6th St, NE_Dec 4 (6).jpg

overview

As part of its Capital Improvement Program, DC Water is replacing existing 12-inch and smaller cast iron water mains in various locations throughout the city. Construction for this project will occur in the Brightwood neighborhood (see construction location map on back). These efforts will help improve water quality and system reliability, increase water pressure in some areas, and maintain adequate flows throughout the system.

 

scope of work

  • Installation of approximately 4,923 linear feet of 3-inch up to 12-inch water mains
  • Replacement of service lines – including free private side replacement of lead and galvanized iron pipe
  • Replacement of fire hydrants and valves
  • Restoration of all surfaces disturbed by the project construction upon completion of the work

 

schedule

  • Construction start: On or about 08/22/22
  • Construction completion: On or about 08/11/23
  • Normal work hours: 9:30 AM to 3:30 PM, Monday through Friday

 

The contractor may, at times, need to work at night or on weekends, dependent upon certain construction activities, or due to inclement weather.

 

Important Information

  • For all planned temporary water service shut-offs, affected residents will be notified 48 hours in advance. Service interruptions should be minimal.
  • Construction activities such as these may cause temporary discolored water or low water pressure. If you experience discolored water, it is recommended that you flush your cold water tap from the lowest point inside your property for approximately 15 minutes. If your water does not clear after this process, please contact DC Water’s Water Quality and Technology Division, or our 24-hr Emergency/Command Center.

 

Traffic

  • Flagging operations and lane closures may be required daily for each construction phase to maintain traffic in the construction work zone.  All Traffic Control Plans will be approved by the District Department of Transportation (DDOT).
  •     At various times during construction, “No Parking” signs may be placed in certain areas in and around the work zone.  Notifications regarding “No Parking” zones will be posted 72 hours prior to construction, as required by DDOT.

 

Partners

DC Water is currently working closely with DDOT to ensure minimal disruption during this project.

Regular updates will also be provided to impacted residents, Advisory Neighborhood Commission 4B, Ward 4 representatives in the Mayor’s Office of Community Relations and Services, and Ward 4 Councilmember Janeese Lewis George and members of her staff.

 

Contact Information

For more information, please contact:

DC Water Project Manager:  William McCanless (202) 515-6594  / William.McCanless@dcwater.com

DC Water Project Contractor: Capitol Paving of DC, Inc. – Geovanni Avila (202) 520-2097

DC Water Water Quality and Technology Division: (202) 612-3440

DC Water 24-hr Emergency/Command Center: (202) 612-3400

DC Water Office of Marketing and Communications: (202) 787-2200

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

West Potomac Park Drive SW
West Potomac Park Drive SW: New Roadway Opening

(Washington, DC) – DC Water will open West Potomac Park Drive SW, a new road constructed as a part of the Potomac River Tunnel (PRT) Project, on Mo

Latest Blog Post
Photo of Great Falls of the Potomac River with fast moving rapids going over the falls
The Critical Need for a More Resilient Water Source and Protecting the One We Have
Source Water Protection Week highlights the case for second water source.
Upcoming Meeting
Date
January 9, 2025
Time
Thursday, 2:30 PM

Upcoming Events