SMALL DIAMETER WATER MAIN REPLACEMENT PROJECT SOUTHWEST WATERFRONT / BUZZARD POINT AREA ADVISORY NEIGHBORHOOD COMMISSION 6D

Capital Improvement Program

overview

As part of its Capital Improvement Program, DC Water is replacing existing 12-inch and smaller cast iron water mains in various locations throughout the city. Construction for this project will occur in the Southwest Waterfront/Buzzard Point area (see construction location map on back). These efforts will help improve water quality and system reliability, increase water pressure in some areas, and maintain adequate flows throughout the system.

 

scope of work

  • Installation of approximately 166 linear feet of 8-inch water mains
  • Replacement of service lines – including free private side replacement of lead and galvanized iron pipe
  • Replacement of fire hydrants and valves
  • Restoration of all surfaces disturbed by the project construction upon completion of the work

 

schedule

  • Construction start: On or about Monday, May 8, 2023
  • Construction completion: On or about Monday, August 14, 2023
  • Normal work hours: 9:30 AM to 3:30 PM, Monday through Friday

 

The contractor may, at times, need to work at night or on weekends, dependent upon certain construction activities, or due to inclement weather.

 

important information

  • For all planned temporary water service shut-offs, affected residents will be notified 48 hours in advance. Service interruptions should be minimal.
  • Construction activities such as these may cause temporary discolored water or low water pressure. If you experience discolored water, it is recommended that you flush your cold water tap from the lowest point inside your property for approximately 15 minutes. If your water does not clear after this process, please contact DC Water’s Water Quality and Technology Division, or our 24-hr Emergency/Command Center.

 

traffic

  • Lane closures and flagging operations may be required daily for each phase of construction to maintain traffic in the construction work zone. All Traffic Control Plans will be approved by the District Department of Transportation (DDOT).
  •     Notifications regarding “No-Parking” zones will be posted 72 hours prior to construction, in certain areas in and around the job site, as required by DDOT.

 

partners

DC Water is currently working closely with DDOT to ensure minimal disruption during this project.

Regular updates will also be provided to impacted area customers, Advisory Neighborhood

Commission 6D, Ward 6 representatives in the Mayor’s Office of Community Relations and Services,

and Ward 6 Councilmember Charles Allen and members of his staff.

 

Contact Information

For more information, please contact

DC Water Project Manager: Michael B. Collins (202) 787-4462 / Michael.Collins2@dcwater.com

DC Water Project Contractor: Gilbane Building Company – Kevin Strupp (571) 551-5041

DC Water Water Quality and Technology Division: (202) 612-3440

DC Water 24-hr Emergency/Command Center: (202) 612-3400

DC Water Office of Marketing and Communications: (202) 787-2200

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

West Potomac Park Drive SW
West Potomac Park Drive SW: New Roadway Opening

(Washington, DC) – DC Water will open West Potomac Park Drive SW, a new road constructed as a part of the Potomac River Tunnel (PRT) Project, on Mo

Latest Blog Post
Photo of Great Falls of the Potomac River with fast moving rapids going over the falls
The Critical Need for a More Resilient Water Source and Protecting the One We Have
Source Water Protection Week highlights the case for second water source.
Upcoming Meeting
Date
January 9, 2025
Time
Thursday, 2:30 PM

Upcoming Events