DC Water's

News & Updates

At DC Water, we understand the importance of keeping our community informed about our services, projects, and achievements. Our news web page serves as a reliable source for the latest information on a range of topics.

contract for construction of the Potomac River Tunnel (PRT)
1 March, 2026

Potomac Interceptor Repairs Update 
March 1, 2026

  • Today marks a milestone, as we reach the three-week point with no overflows entering the Potomac River. The last release to reach the river occurred on February 8.
  • On February 28, National Park Service (NPS) issued a Special Use Permit for the repair, rehabilitation, and environmental restoration of the Potomac Interceptor and the C&O Canal National ...
contract for construction of the Potomac River Tunnel (PRT)
28 February, 2026

Potomac Interceptor Repairs Update
February 28, 2026

  • The bypass pumping system continues to divert wastewater around the collapse site and back into the Potomac Interceptor, preventing any overflows from reaching the Potomac River in nearly three weeks. The last time an overflow reached the river was 20 days ago, February 8.
  • Crews continue to clean the pipe and progress is being made to remove the ...
contract for construction of the Potomac River Tunnel (PRT)
27 February, 2026

DC Water will be performing repairs to the Rock Creek Main Interceptor (RCMI) within the West End and Georgetown Neighborhoods. This will require temporary lane closures beginning tonight, February 27, at 8 PM through Monday, March 2, at 5 AM.

Photo of workers doing environmental rehab site preps
27 February, 2026

No overflows reaching the Potomac River for 19 days. The last release to enter the river occurred on February 8. Crews were able to reach some of the additional large rocks downstream of the collapsed section and remove them without additional excavation. Cleaning continues in the area upstream of the damaged section of the Potomac Interceptor to remove muck, debris, and smaller rocks.

Graphic with meeting information
26 February, 2026

DC Water is inviting Maryland residents to join us tonight for a community meeting at Walt Whitman High School at 7 p.m. for an update about ongoing repair efforts on a section of the Potomac Interceptor sewer line that failed, directly impacting the surrounding Montgomery County communities. The meeting will provide an opportunity for residents to ask questions, learn about planned environmental ...

contract for construction of the Potomac River Tunnel (PRT)
26 February, 2026

Crews continue work to clean the remaining debris upstream and downstream of the damaged Potomac Interceptor Pipe, with no overflows entering the Potomac River in 18 days.
A rock and debris dam that had been blocking the pipe has been removed, but some large rocks and boulders remain in other sections of the pipe and may require additional excavation to remove.

Photo of remaining rocks and debris
25 February, 2026

DC Water has made significant progress toward repairing a damaged section of the Potomac Interceptor. Crews are nearly done removing a rock and debris dam that was blocking the pipe. Several feet of rocks and debris remain to be cleared and is expected to be completed overnight. Ongoing work continues to maintain bypass pumping operations 24/7 with no overflows reported for 17 days.

Graphic with the information for the Community Meeting
24 February, 2026

As DC Water continues repair efforts on the Potomac Interceptor sewer line, we want to provide an opportunity for the community to engage with us on Wednesday, February 25, to ask questions, and learn more about the response, impacts to the Potomac River, and next steps in the emergency repair and long-term rehabilitation efforts.

Trench box being installed to expand excavated area
24 February, 2026

Repairs are moving forward, with crews closer to reaching a debris dam and large rocks blocking a section of the damaged Potomac Interceptor. Work has been completed to fully extend the excavation site and install trench boxes to stabilize and isolate the additional pipe sections. No overflows entering the Potomac River have occurred in 16 days.

Photo of extended excavation site with trench boxes
23 February, 2026

The excavation around a damaged section of the Potomac Interceptor has been extended and trench boxes installed to provide shoring and stability. This doubles the size of the excavated area, to connect the collapse site with a downstream access point to the Potomac Interceptor.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Picture of new bike pedestrian path and traffic detour
New Path for Capital Crescent Trail Opens at Georgetown Waterfront Park

DC CLEAN RIVERS – POTOMAC RIVER TUNNEL PROJECT
If you bike, drive, or walk through Georgetown, we’ve got changes starting this week around the Potomac River Tunnel construction on Water Street NW. The Capital Crescent Trail has a new temporary detour through Georgetown Waterfront Park, open now for cyclists between 33rd and Potomac streets NW.

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.