DC Water's

News & Updates

At DC Water, we understand the importance of keeping our community informed about our services, projects, and achievements. Our news web page serves as a reliable source for the latest information on a range of topics.

CEO David L. Gadis with HSEMA, EPA and USACE
22 February, 2026

DC Water crews are working around the clock to keep the Potomac Interceptor repair site safe as another storm approaches. Since February 8, there have been no overflows to the Potomac River, and efforts are underway to bolster pump capacity and manage stormwater runoff due to expected heavy rain and snow that could flood the pumping site and endanger pumping operations.

workers inside pipe cleaned of rocks and debris
21 February, 2026

Potomac Interceptor Repair Update
February 21, 2026

  • For nearly two weeks, no overflows have entered the Potomac River. The last release to the river occurred on February 8.
  • Crews are continuing to remove debris and large rocks from inside the damaged pipe section.
  • An initial assessment of the damaged pipe section determined the remaining intact structure downstream, which is blocked by an extensive ...
Graphic with details about the two community meetings.
21 February, 2026

DC Water will host two community meetings to provide a comprehensive update on the Potomac Interceptor response, current system status, and next steps in emergency repair and long-term rehabilitation efforts.

The meetings will provide a structured overview of:

  • What occurred
  • Immediate response actions
  • Current repair timeline
  • Long-term Capital Improvement Plan commitments

DC Water officials and technical ...

workers removing a large boulder in damaged pipe
20 February, 2026

Highlights
 

  • Today marks the 12th consecutive day with no new overflow events entering the Potomac River or impacting surface waters.
  • The bulkhead installed in the Potomac Interceptor at I-495 continues to function as designed, preventing flow from moving downstream toward the damaged section of pipe.
  • Bypass pumping remains fully operational, despite heavy rains and snowmelt increasing flow.
  • Crews ...
Collapse site with workers inside
19 February, 2026

DC Mayor Muriel Bowser Visits Site as Crews Make Progress on Repairs

DC Water has successfully reached the damaged section of the Potomac Interceptor, marking a critical step in the ongoing damage assessment and repair efforts. Crews today are manually digging out the affected area, carefully removing sludge, soil, and debris from the collapsed pipe.

Image of the collapse site drained of water
18 February, 2026

Efforts to isolate the damaged section of pipe are moving forward. Engineers are on site and preparations are underway to permanently install a steel bulkhead gate that will cut off flow to the collapse site in combination with an enhanced bypass pumping system that will continue to divert wastewater around the failure and into the Potomac Interceptor further downstream. Once fully activated, the ...

Enhanced bypass with pumps and bulkhead gate in position
17 February, 2026

Potomac Interceptor Collapse Update
Tuesday, February 17, 2026

  • No overflow events impacting surface waters were reported overnight. No overflow events impacting surface waters have been reported since February 9, 2026.
  • DC Water continues making significant progress toward stabilizing the Potomac Interceptor, with crews successfully testing the bulkhead system and bypass pumps. Six of the seven new ...
Photo fo new access pit for enhanced bypass and pumps
16 February, 2026

Emergency repair expected to take 4-6 weeks, followed by long-term rehabilitation

DC Water crews and its contractors, working under challenging conditions over the past month, are nearing completion of an enhanced bypass system that will allow emergency repairs to begin on a damaged section of the Potomac Interceptor.

Bypass pumps in operation to reroute wastewater around the break
15 February, 2026

Potomac Interceptor Repairs Update

February 15, 2026 

  • No overflow events impacting surface waters have been reported in the past 24 hours.
  • The four high-capacity bypass pumps installed this week are now fully primed and operational, increasing overall system capacity and reliability. 
  • In addition, the third flume at the downstream end of the canal near Lock 10 is now active and conveying wastewater ...
Photo of access pit upstream with four pumps lined up ready for installation
14 February, 2026

Crews have completed construction of the two new access pits to support full installation of the enhanced bypass pumping system. Three high-capacity bypass pumps have been installed and are operational, with a fourth pump expected to be activated later tonight or early Sunday ahead of the forecasted weather to help manage anticipated higher flows associated with rainfall and snowmelt.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Map of lane closure
Traffic Advisory: Rock Creek and Potomac Parkway NW Lane Closure Beginning Jan 19

Beginning on or about January 19, 2026, weather permitting, DC Water will implement a temporary lane closure on Rock Creek and Potomac Parkway NW b

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting
Date
February 26, 2026
Thursday, 9:30 AM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.