EMERGENCY WATER OUTAGE
Feb 09, 2026 | 01:00 AM

Emergency Water Outage
Feb 08, 2026 | 03:00 PM

Emergency Water Outage
Feb 08, 2026 | 02:00 PM

DC Water's

News & Updates

At DC Water, we understand the importance of keeping our community informed about our services, projects, and achievements. Our news web page serves as a reliable source for the latest information on a range of topics.

contract for construction of the Potomac River Tunnel (PRT)
8 February, 2026

Work continues on the Potomac Interceptor, a section of which collapsed on January 19, along Clara Barton Parkway and the I-495 interchange and C & O Canal Historical Park causing a sanitary sewer overflow. 

A bypass system established five days after the overflow occurred continues to successfully divert wastewater around the collapse site and back into the Potomac Interceptor further downstream.  ...

contract for construction of the Potomac River Tunnel (PRT)
8 February, 2026

DC Water is taking emergency measures with the immediate and ongoing closure of all northbound lanes of 14th Street between L Street NW and Thomas Circle, due to the imminent risk of collapse posed by an abandoned, century-old, brick-lined sewer tunnel beneath the roadway.

Trench boxes at construction site for new pit accessing Potomac Interceptor Upstream
7 February, 2026

DC Water and its contractors continue to make progress constructing new access points to the Potomac Interceptor, one upstream of the damaged section, and an additional entry downstream to divert more wastewater flow from the pipe. These access points will allow crews to install a bulkhead, blocking flow in the pipe upstream of the collapsed area, keeping the site as dry as possible so crews can ...

Photo of giant rock and boulder removed
6 February, 2026

DC Water is releasing new findings regarding the environmental impacts following the January 19, collapse in a section of the Potomac Interceptor. Based on flow monitoring data collected before and after interim bypass pumping was activated, DC Water estimates approximately 243 million gallons of wastewater has overflowed from the collapse site.

Image of rock blockage taken by CCTV inside the Potomac Interceptor downstream of the collapse
5 February, 2026

Update on Extended Repairs, Safety Measures, and Water Quality Monitoring

Overnight CCTV inspection of the Potomac Interceptor revealed the blockage inside the collapsed sewer line is far more significant, showing a large rock dam stretching approximately 30 feet downstream of the original failure.

Three workers over the pit accessing the Potomac Interceptor for Cleaning
4 February, 2026

DC Water and its contractor are working to clean debris from a damaged section of the Potomac Interceptor, a sanitary sewer line that collapsed on January 19, along Clara Barton Parkway and the 495 interchange and the C & O Canal National Historical Park. While limited overflows occurred earlier in the week, no overflows from the site were reported today. Here is an update on the cleaning and ...

Picture of the work site where cleaning is taking place and pumps being installed
3 February, 2026

Potomac Interceptor Overflow Update
Tuesday, February 3, 2026

 Work to clean and repair the damaged section of the Potomac Interceptor continues, though progress is being slowed by large boulders and rocks inside the pipe. Meanwhile, increased flow from groundwater infiltration attributed to snowmelt, along with periodic clogging of the bypass pumps, at times, resulted in minor overflows near the ...

contract for construction of the Potomac River Tunnel (PRT)
2 February, 2026

Cleaning efforts continue today on the Potomac Interceptor, to remove debris and obstructions inside the damaged section of the sewer line. The 72-inch pipe collapsed two weeks ago along Clara Barton Parkway and the 495 interchange and the C & O Canal National Historical Park in Montgomery County, Md.  Here is an update on the ongoing work. 

Potomac Interceptor Overflow Update
Monday, February 2 ...

Potomac Interceptor Access Point showing sewer line where vacuum hoses are going in to clear debris
1 February, 2026

DC Water and its contractor are working to clean out the damaged section of the Potomac Interceptor, a sanitary sewer line which overflowed January 19, along Clara Barton Parkway and the 495 interchange and into the C & O Canal National Historical Park. Below is an update on the work being done and progress to date. 

Potomac Interceptor Update
Sunday, February 1, 2026

Containment

  • Overflow from the ...
Truck mounted vacuum cleaning the Potomac Interceptor
31 January, 2026
DC Water and its contractor continue work to mitigate the sanitary sewer overflow that occurred on January 19, from the Potomac Interceptor, along Clara Barton Parkway and the 495 interchange and into the C& O Canal National Historical Park. Below is an update on the progress. 
 
Potomac Interceptor Overflow Update
January 31, 2026
 
Containment
  • The overflow remains contained for now, with no overflows ...

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Picture of new bike pedestrian path and traffic detour
New Path for Capital Crescent Trail Opens at Georgetown Waterfront Park

DC CLEAN RIVERS – POTOMAC RIVER TUNNEL PROJECT
If you bike, drive, or walk through Georgetown, we’ve got changes starting this week around the Potomac River Tunnel construction on Water Street NW. The Capital Crescent Trail has a new temporary detour through Georgetown Waterfront Park, open now for cyclists between 33rd and Potomac streets NW.

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting
Date
February 19, 2026
Thursday, 9:30 AM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 40% of the last 3 payments made and in the new fiscal year 50% will be credited. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.